Qualification
DQ, IQ, OQ and PQ explained
DQ, IQ, OQ and PQ explained: objectives, test points and evidence for each qualification stage, with practical examples from cleanrooms, HVAC and compressed air.
· 9 min read
Cleanliness is a state. Without evidence, it remains a claim.
Service 01
DQ, IQ, OQ and PQ for cleanrooms, HVAC systems, compressed air, pharmaceutical water and process equipment. We derive the test scope from the risk assessment.
What it is about
Qualification demonstrates that facilities, systems and equipment are fit for their intended use. Annex 15 of the EU GMP Guide requires it, and 21 CFR Part 211 sets comparable requirements for buildings and equipment. We start with the qualification master plan and the risk assessment. Together they determine which object is tested and to what depth. Test plans contain acceptance criteria that are approved before testing. We record deviations with an assessment and an action. The result is a report your quality unit can approve.
An aseptic area gets the full scope. For a non-classified room, complete documentation comes first. The justification is in the risk assessment.
Every test item has an acceptance criterion with a traceable origin: from the DQ, the URS or a standard.
Critical deviations are closed before the report is approved. Non-critical ones are assessed and tracked with a due date and an owner.
Approach
Define objects, scope per object and responsibilities. Assess risks to product and patient.
Define test items, methods and acceptance criteria and have them approved in advance.
Perform or witness tests, record expected and actual values, secure raw data and evidence.
Evaluate results, close deviations, prepare approval and qualification status.
QMP
Define objects, interfaces and scope
Risk assessment
shows what is critical for product and patient
URS
GMP-relevant requirements only
DQ
User requirements against supplier specification
IQ · OQ · PQ
Expected against actual, with evidence
Approval
Report, then requalification
Sample documents
Unique IDs, acceptance criteria before testing, approval fields and consistent references.
All documents shown are fictitious samples in the X-Mon document design. They show layout and structure and contain no customer data and no extracts from regulations. Click to enlarge.
Questions
That depends on the project. We write plans and protocols, carry out or witness tests and write the reports. Whether a specialist contractor takes on individual measurements is clearly defined in our quotation.
They are two qualification objects. Where one ends and the other begins is defined as an interface in the qualification plan, for example whether terminal HEPA filters and room pressure sensors belong to the HVAC system or to the room. A room also has its own OQ, for example for airlock door interlocks and airlock indicators. In the OQ both come together: pressure cascade, airflow direction, cleanliness grade and recovery time can only be demonstrated in the finished room with the system running. Which protocol these tests belong to follows from the interface.
Yes. We write the plan and protocol, place our calibrated data loggers at risk-based measuring points, evaluate the data and write the report, including a recommendation on where the permanent monitoring sensors belong. Where storage areas are part of a room that is qualified anyway, mapping is part of the room or HVAC qualification. We do not map transport routes.
Yes. We start with a short review of the current status: what is complete, what is open and where evidence or the link to a requirement is missing.
That is included. After a change, the risk assessment shows which tests are needed. For the periodic review we look at calibration trends, maintenance, deviations and the sum of small changes.
Insights
Qualification
DQ, IQ, OQ and PQ explained: objectives, test points and evidence for each qualification stage, with practical examples from cleanrooms, HVAC and compressed air.
· 9 min read
Qualification
What belongs in a room book, how it leads to the air volume schedule, and where the qualification interface between the room and the HVAC system lies.
· 8 min read
Qualification
Why warehouses, cold rooms and climatic chambers are mapped, how measuring points, duration and load are defined, and what EU GDP, EU GMP and WHO say.
· 8 min read
Contact
You will get a personal reply with a first assessment of scope and approach.